Summons issued + partial stop-work order
DOB inspector cited an 8'+ fence/guardrail at 316 Eckford St. No permit existed, so Summons 039159250K was issued with a cure date of Nov 3 and a hearing on Nov 12. Read the summons.
fence.uh-oh.wtf
On September 4, 2025 the NYC Department of Buildings issued Summons 039159250K for an over-height backyard fence built without a permit. The fence was removed and the OATH penalty was paid, but a $10,000 Work-Without-Permit civil penalty was assessed and a partial Stop Work Order remains active. This page documents both the 2025 penalty track and the 2026 legalization track — the permit filing that can reduce the penalty and lift the order. Here’s the timeline and every document filed so far.
DOB inspector cited an 8'+ fence/guardrail at 316 Eckford St. No permit existed, so Summons 039159250K was issued with a cure date of Nov 3 and a hearing on Nov 12. Read the summons.
Andrew Fenlon removed the fence, photographed the site, and completed the AEU2 affidavit plus the AEU20 statement describing the removal. AEU2 · AEU20 & photos.
The $1,250 OATH fine (plus fees) for the summons was paid via CityPay. The receipt is bundled with the AEU20 packet. See the receipt.
Joseph Russo authorized Andrew Fenlon to prepare and submit all DOB correction paperwork on behalf of the Linda J. Salop Irrevocable Trust. View authorization.
DOBNOW disapproved tracking #COC0366947 because a Work-Without-Permit civil penalty was still due. Read the notice.
We emailed Brooklyn PER11 Plan Exam with a notarized PER11 form, AEU2/AEU20, photos, and the summons, asking DOB to assess the WWP penalty because no legalization permit exists. Follow-ups on Nov 10 and Nov 20 reiterated the request. Email thread · PER11 form.
PER11 unit replied that a $10,000 WWP civil penalty is due for the summons and asked (again) for a sworn owner affidavit plus timestamped photos—even though those were already filed. See the sheet.
The corrected condition remains posted in DOBNOW, but the certificate stays disapproved until the WWP civil penalty is paid/credited. Portal screenshots still show a partial stop-work order on the property. DOBNOW screenshots.
Big Orange Expediting, the original expediter on the file, emailed DOB four or more times over a month simply to get the Stop Work Order rescission inspection scheduled. DOB did not reply during this window. The stonewalling is a recurring pattern on this case: the bottleneck has consistently been DOB’s own response time rather than the expediters.
DOB’s OBM Stop Work Order unit finally replied. The unit explained that the Work-Without-Permit civil penalty must be resolved and that the path to lifting the Stop Work Order is to file an L2 form with the Brooklyn borough commissioner’s office to waive the $10,000 penalty. Once the penalty is resolved and the cashier receipt is uploaded to the Certificate of Correction, the SWO can be rescinded. This explicit lift-path guidance sat unread in the inbox and was not acted on for months.
Andrew asked attorney Michael Longyear for an architect referral. Longyear forwarded a proposal from Phillip Anzalone, RA (Atelier Architecture 64) to consult on a legalization filing for the rear-yard fence and wall.
Longyear formally introduced Phillip Anzalone to Andrew, opening direct contact with the architect who would lead the legalization effort — the filing that can convert the $10,000 maximum WWP penalty into the actual, lower amount.
Phillip Anzalone made his first site visit to 316 Eckford. He found the purchased fence material staged in the rear yard and confirmed that the original unpermitted fence had already been removed back in September 2025.
Phillip sent a six-step Phase 1 plan: draft the rear-yard fence and landscaping for DOB approval, file for a permit, complete the rear-yard work, sign off and close the job, lift the Stop Work Order, and clear the property records (the WWP penalty and the missing Certificate of Occupancy). Andrew approved the plan.
Phillip forwarded filing-rep Sarah Butcher’s proposal, flagging that her draft title incorrectly described the work as a ‘construction fence’ — a scope label that needed correcting before any DOB submission.
Phillip stressed keeping Phase 1 narrow — just lift the Stop Work Order, clear the records, and install the on-hand fence material (roughly a day’s work) — so that DOB’s focus stays on the rear yard and does not spread to the rest of the building. Andrew agreed and requested a call.
Andrew raised a zoning finding from his own research: the structure is better understood as an up-to-8-foot wall between the parking lot and the backyard than as a continuous fence, and he argued the legalization permit should cover that wall. A call was arranged to reconcile the fence-versus-wall question — the key open design decision — before filing.
Andrew forwarded the Big Orange land survey (dated April 25, 2024) to Phillip as supporting evidence for the wall approach.
Phillip introduced Sarah Butcher as the DOB filing representative. Andrew signed her proposal and she returned the fully executed agreement, formally engaging her to handle the DOB submission.
Phillip returned his countersigned agreement, formally taking on the project as architect of record for the legalization filing.
Sarah Butcher reported she was working on the Stop Work Order and the violation and needed current rear-yard photographs; she requested site access on July 1 or 2.
Sarah Butcher visited the site and photographed the rear yard. Andrew shared the documentation site and noted that no DOB NOW account number existed for the property, only the email login. Sarah indicated the team would get started on the filing.
Andrew nudged Sarah Butcher for a status update on the filing, copying Phillip. No reply was received.
With no email reply from Phillip since June 24, Andrew texted him directly for a status on the filing and the $10,000 penalty path. Phillip did not reply the same day. As of this date the Stop Work Order remains active, the $10,000 WWP civil penalty appears unpaid, and the legalization filing’s progress is unconfirmed.
The 2025 penalty track left the property with a $10,000 Work-Without-Permit civil penalty (assessed December 2, 2025 because no legalization application was on file) and an active partial Stop Work Order. The 2026 legalization track is the response: filing a proper permit for a compliant rear-yard fence/wall is the mechanism DOB needs to convert that $10,000 maximum into the real, lower amount, and to lift the Stop Work Order. Filing is what reduces the penalty; delay means the $10,000 sticks.
When DOB assessed the Work-Without-Permit penalty in December 2025, it could not calculate the actual amount because no legalization application had been filed, so it imposed the $10,000 maximum. A legalization permit gives DOB the application it needs to determine the true, lower penalty. It is also the path to resolving the partial Stop Work Order that has been active on the rear-yard work since the original summons. In short, the permit is not just about building a fence — it is the instrument that lowers the penalty and clears the order. The longer it takes to file, the longer the maximum penalty and the Stop Work Order remain in place.
On January 21, 2026, DOB’s OBM Stop Work Order unit laid out the route to lift the order: the owner can file an L2 form with the borough commissioner’s office to waive or resolve the Work-Without-Permit penalty, after which the SWO can be rescinded. A copy of the December 2 penalty assessment is to accompany the L2 submission. Once the penalty is resolved (paid or waived), the receipt is uploaded to the Certificate of Correction and the order can be lifted. This L2 route runs alongside the legalization permit: the permit gives DOB the application to recalculate the penalty, and the L2 is the administrative step that clears it so the Stop Work Order comes off.
Architect Phillip Anzalone laid out a six-step Phase 1 plan focused narrowly on the rear-yard fence and landscaping — the exterior work tied to the original violation. The aim is to get a compliant fence/wall permitted, built, and signed off, then use that to clear the property’s open records. The decorative and later permitted work is deliberately set aside.
Before the permit can be filed, there is an unresolved design question about what the structure actually is and what the permit should cover. Based on his own zoning research, the owner concludes that the original structure was an up-to-eight-foot wall between the parking lot and the backyard rather than a continuous fence, and argues the permit should cover that wall. The architect’s discipline is the opposite: keep Phase 1 minimal — a simple rear-yard fence plus landscaping — so that DOB’s review stays narrow and does not spread to the rest of the building. The wall concept is not new: the prior expediter’s January 20, 2026 proposal was for a six-foot concrete-and-concrete-block rear fence/wall, so the idea predates the current architect and is grounded in the earlier survey work. Reconciling fence-versus-wall is the key open design decision, and it is presented here as an open question, not a resolved one.
The legalization track involves several parties of record, each with a defined role. They are named here by role only.
The 2025-track records above are archived on this site. 2026-track correspondence — the architect and filing-rep agreements, the DOB L2 / borough-commissioner email of Jan 21, 2026, and the Big Orange fence/wall proposal — is not yet posted; this page will be updated as those are filed.